Project Description

____________________________________

The Phases of the Project Were the Following:

  • Phase 1: The Cheia Representative Basin (socio-economic aspects), sensibility to floods of the area
  • Phase 2: Collection of data from the local hydrometric network existent at Cheia
  • Phase 3: Warning procedures of the population and tourists from Cheia in case of flash floods.
  • Phase 4: Preparation and testing of the educational programme through the instruction of the population in case of floods
    and loss mitigation methods (including the operation of the warning system)
  • Phase 5: Dissemination of the experience accumulated within the project for other areas prone to flash floods
  • Phase 6: The drawing up of the technical and financial report

Final result

It was elaborated a report containing the adaptation modality of the warning system and education of the population in case of flash floods. The results will serve as model for river basins with similar physical – geographical conditions. [click here to see the original report]

__________________________

Caracteristici generale fizico-geografice ale subbazinelor din bazinul experimental Cheia:

Râul

Statia hidrometrica

An înfiintare

F
(km2)

H
(m)

I baz
(‰)


Cheita

Cheia

1975

21

1320

0.397

Cucu

Cheia

1975

1.2

1096

0.201

Gropsoare

Cheia

1995

8.82

1290

0.376

Zaganu

Cheia

1995

2.87

1073

0.182

Baicu

Cheia

1995

1.18

1004

0.042

Tampa

Cheia

1975

13.9

1213

0.27

Ciobu

Cheia

1975

1.78

1085

0.292

Teleajen

Cheia

1975

41.3

1263

0.339

 

________________________________________________________________________________________

PREZENTATION | PROJECT DESCRIPTION | FLOOD PROGNOSYS | ACCIDENTS AVOIDANCE | CONTACT

 

© INHGA 2006 - all rights reserved | IE 5+; 1024x768; 32bit | neoCreatio Concept _